Kashagan Main Works Tranche 1, 2, 3 Project

PROJECT DETAILS

LOCATION: Atyrau, Kazakhstan

CONTRACTOR: North Caspian Contractors B.V. (NCC)

CONSTRUCTION PERIOD: 39 Months

Project Description:

Tranche 1,2

Project Detail:

The project is construction of main pipe rack, oil process units and gas compression unit for Tranche 1 and 2 of petroleum process facility located 35 km northeast of Karabatan region, Atyrau, Republic of Kazakhstan. Scope of project is; supply of all civil works materials, paint, insulation, support and all consumables, execution of civil works, construction of industrial buildings, fabrication and erection of steel structures, prefabrication of piping spools and installation, installation of equipment, painting and insulation works.

Building construction works

  • Buildings: 11 ea
  • Area (Closed): 17.014 m2
  • Cladding Works: 28.410 m2

Civil works

  • Concreting: 12.300 m3
  • Road: 2.100 m2 asphalt

Structural steel erection works

  • Steel Erection: 1.120 ton

Equipment erection works

  • 2,682 ea different size equipment

Piping works

  • Aboveground Piping: 39.132 WDI welding
  • Underground Piping: 12.179 WDI welding

Cable works

  • Aboveground Cabling: 388.643 m
  • Underground Cabling: 108.800 m

Tranche 3

Project Detail:

The project is construction of Main Pipe Rack for Tranche 3, Oil Processing Unit for Tranche 3 and Gas Compression Unit 361 of Petroleum Process Facility located 35 km northeast of Karabatan region, Atyrau, Republic of Kazakhstan. Scope of project is; supply of all civil works materials, paint, insulation, support and all consumables, execution of civil works, construction of industrial buildings, fabrication and erection of steel structures, prefabrication of piping spools and installation, installation of equipment, electrical and instrumentation works, painting and insulation works.

Civil Works

  • Concreting: 2.337 m3 (structural), 14.972 m3 (paving)
  • Roads: 8.263 m2 asphalt

Structural steel erection works

  • Steel Erection: 2.916 ton

Equipment erection works

  • 99 ea different size equipment

Piping works

  • 169.290 WDI welding

Painting works

  • Structural Steel: 72.734 m2
  • Piping: 18.411 m2

Insulation works

  • Equipment: 2,899 m2
  • Piping: 9.915 m2